This methodology will explain the procedure for doing the RCC Parapet wall.
Approximate 12 m³.
As applicable to respective Structure – Layout & RCC Details of Terrace Slab and Beams for Control room, drg IN1024-01UAB-&C1.H060-711637 Rev- D (1 of 3).
Approved Agency
The progress will be as per requirement.
⚡ Power supply: Generators for lighting in General shift (8:00 Am to 8:00 Pm).
💡 Lighting: Halogen & lighting mast.
Actual resource plan (tools & manpower) reviewed & finalized by site in-charge.
| Item Description | Quantity | Remarks |
|---|---|---|
| Mechanical Tool Kit | ||
| Spanner Set / Torque Wrench | ||
| Guide rope | ||
| Spades, digging bars etc | ||
| Cherry Picker or 4 Wheel Ladder | ||
| Ladders | ||
| Electrician Tool Kit | ||
| Gas Filling and Evacuation Kit |
| Type | Name of manpower | Quantity |
|---|---|---|
| 1 | Engineer | |
| 2 | Safety Officer/Engineer | |
| 3 | As Required | |
| 4 | Safety Supervisor | |
| 5 | Electricians | |
| 6 | Supervisor | |
| 7 | Labor |
Attached – see separate JHA / risk register.
Site In charge responsible for installation & commissioning.
Site Engineer supervises construction activities and workmen.
Quality Manager responsible for overall quality (supply, erection, testing).
| Material | Ratio | Weight (kg/m³) | Remarks |
|---|---|---|---|
| Cement (OPC 43/53) | 1 | 425 – 450 | ~8.5 bags |
| Fine Aggregate (Coarse sand) | 1 | 550 – 620 | Zone II |
| Coarse Aggregate (20mm & 10mm) | 2 | 1150 – 1250 | 60% 20mm + 40% 10mm |
| Water | 0.45 | 190 – 200 ltr | w/c ratio ≤0.45 |
* Typical design mix (IS 456) – actual may vary by source. Fine aggregate = coarse sand (zone II).
🔹 Cement : 425 kg
🔹 Coarse sand (fine agg) : 600 kg
🔹 Coarse aggregate (20mm down) : 1200 kg
🔹 Water : 190 litres
(proportion 1:1.4:2.8 approx · standard 1:1:2 by volume)
| Activity | Output (mason + helper) |
|---|---|
| Rebar fixing (kg/day) | 80–120 kg |
| Formwork erection (m²) | 8–12 m² |
| Concreting (including vibrator) | 3–5 m³ |
Er. Kuljit Singh · Arshavtar.in